FCU CHALLENGE FROM DAY 10 TO DAY 12 : BUILD A HOUSE IN 30 DAYS
MY HOMESCHOOLING JOURNAL
DAY 10 :
1 OF OCTOBER, 2010.
Officially Monson Barat Daya that started in Mei was ended by the early of October. This meant that the down season in Langkawi was ended after five months poured by a heavy rain. It was a good news for tourism sectors.
On day 10, we started to attach the horizontal iron bar skeleton between the pillars.
All these were about iron. Iron bars, iron rods and iron wires. Everything must be attached tightly.
The play wood was being cut into pieces. We were going to make form works that will hold the cement around the pillars. The dust from the play wood really bothered me....I should put on the face mask like my brother on the first place.
LETS VIEW OUR VIDEO ON DAY 10:
DAY 11 :
2 OF OCTOBER, 2010.
On day 10, FCU got the invitation from Langkawi Sepak Raga Club to join the close competition that would be held on the next day. How about our project? Would we sacrifice our precious time to this competition that we never prepared? Since it was a special request from the chairman of the club, FCU sent its three best players to colour the tournament. Of course,.......I was not included.
TIARA HOTEL...where the tournament took place. It was a big hotel. I liked the whole design of the hotel. Just like a palace in a fairytale. The back view of hotel was a natural garden of mangrove trees around a big lake. In the front of the Tiara Hotel was the magnificent sea view that for sure everybody loved it.
Me....amongst the sepak raga players. They came from all over Langkawi. Of course..I was not in FCU TEAM. Am I the youngest of all? I guess so since I am the smallest of all.
FCU team was in red T-Shirt. Ready to strike!!
I was proud of all of you. GO..FCU GO...!!! My three elder brothers managed to win the first game. Good enough for those who seldom practice.....!!!
My brother Tajrid and me were FCUPRODUCTION crew. We were here to help FCUPRODUCTION MANAGER to take videos of the tournament. It was great to have a change....at least a day from the house project.
As a crew, we had to follow him every where...upstairs and downstairs. Yes sir!! No complained.
I was setting a dolly track for production manager to shoot the video clips.
We were shooting from the second foor of the hotel.
Happy to view our video on the tournament.
LETS VIEW OUR VIDEO ON DAY 11:
DAY 12 :
3 OF OCTOBER, 2010.
For a few days we were doing the same thing..iron skeleton pillars. This was the most important part of a building. We could get different grade of iron. The cheap one or the more expensive one. Better used the expensive one. Just in case of emergency...I mean the earthquake...the house would stand any consequence, Insyaallah. Just be prepared !!
Almost all the pillars were attached by the horizontal iron skeletons.
The next step was putting the form works around the horizontal iron skeletons.